[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149889":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149889,802,2,"多选题","土方开挖施工质量控制中，下列表述正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","隧道外轮廓线的控制，宜用隧道断面仪",true,{"key":16,"text":17,"correct":14},"B","按设计要求确定开挖方式，经试验选择开挖步序",{"key":19,"text":20,"correct":21},"C","每开挖一榀钢拱架的间距，应及时支护、喷锚、闭合，可适当超挖",false,{"key":23,"text":24,"correct":21},"D","在稳定性好的地层中停止开挖，或停止作业时间较长时，应及时喷射混凝土封闭开挖面",{"key":26,"text":27,"correct":21},"E","相向开挖的两个开挖面相距约2倍管（隧）径时，可同时开挖","AB","2020教材P370 \u002F 2019教材P372 二、土方开挖、初期支护施工质量控制：（一）土方开挖:1、宜用激光准直仪控制中线和隧道断面仪控制外轮廓线。2、按设计要求确定开挖方式，经试验选择开挖步序。3、每开挖一榀钢拱架的间距，应及时架设支护、喷锚、形成闭合，严禁超挖。4、在稳定性差的地层中停止开挖，或停止作业时间较长时，应及时喷射混凝土封闭开挖面。5、相向开挖的两个开挖面相距约2倍管（隧）径时，应停止一个开挖面作业，进行封闭，由另一个开挖面作贯通开挖。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]