[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149887":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149887,802,2,"多选题","喷射混凝土施工中，下列表述正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","喷射作业分段、分层进行，喷射顺序由下而上",true,{"key":16,"text":17,"correct":18},"B","喷头应保持垂直于工作面，喷头距工作面不宜大于2m",false,{"key":20,"text":21,"correct":14},"C","分层喷射时，应在前一层混凝土终凝后进行",{"key":23,"text":24,"correct":14},"D","喷射混凝土终凝2h后进行养护，时间不小于14d",{"key":26,"text":27,"correct":18},"E","喷射混凝土养护，冬期宜洒水养护","ACD","2020教材P371 \u002F 2019教材P372 二、土方开挖、初期支护施工质量控制：（二）初期支护施工：（4）喷射混凝土施工：1）喷射作业分段、分层进行，喷射顺序由下而上。2）喷头应保证垂直于工作面，喷头距工作面不宜大于1m。3）一次喷射混凝土的厚度：侧壁宜为70-100mm，拱部宜为50-60mm；分层喷射时，应在前一层混凝土终凝后进行。4）钢筋网的喷射混凝土保护层不应小于20mm。5）喷射混凝土终凝2h后进行养护，时间不小于14h；冬期不得洒水养护；混凝土强度低于6Mpa时不得受冻。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]