[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149884":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149884,802,2,"多选题","关于地铁车站混凝土浇筑的说法，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","混凝土灌注前，隐蔽工程检查必须合格",true,{"key":16,"text":17,"correct":18},"B","底板混凝土应左右对称、水平、分层连续灌注",false,{"key":20,"text":21,"correct":18},"C","墙体混凝土应沿线路方向分层留台阶灌注",{"key":23,"text":24,"correct":14},"D","顶板混凝土应连续水平、分台阶由边墙、中墙分别向结构中间方向灌注",{"key":26,"text":27,"correct":14},"E","混凝土柱可单独施工，并应水平、分层灌注","ADE","2020教材P368 \u002F 2019教材P370 （6）浇筑混凝土前应清除模内杂物，隐蔽工程验收合格后，方可灌注混凝土。混凝土灌注地点应采取防止暴晒和雨淋措施。（7）底板混凝土应沿线路方向分层留台阶灌注，灌注至高程初凝前，应用表面振捣器振捣一遍后抹面；墙体混凝土左右对称、水平、分层连续灌注，至顶板交界处间歇1-1.5h，然后再灌注顶板混凝土；顶板混凝土连续水平、分台阶由边墙、中墙分别向结构中间方向灌注。灌注至高程初凝前，应用表面振捣器振捣一遍后抹面；混凝土柱可单独施工，并应水平、分层灌注。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]