[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149883":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149883,802,2,"多选题","地铁车站的质量控制原则有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","编制施工组织设计，经批准后组织方可用于指导施工",true,{"key":16,"text":17,"correct":14},"B","工程施工应以批准后的设计文件为依据",{"key":19,"text":20,"correct":14},"C","采用的原材料、预制品、设备等，应符合国家现行的有关技术标准规定",{"key":22,"text":23,"correct":14},"D","施工设备应有铭牌",{"key":25,"text":26,"correct":27},"E","采用和推广经鉴定并批准的新设备可与常规设备一样直接应用于工程",false,"ABCD","2020教材P367 \u002F 2019教材P369 一、质量控制原则：1、工程开工前，必须根据设计文件经现场调查后，编制施工组织设计、进行质量策划，批准后组织实施。2、工程施工应以批准后的设计文件为依据，如需修改，应取得设计单位同意并签署设计变更或洽商记录后方可实施。3、采用的原材料、预制品、设备等，应符合国家现行的有关技术标准规定。产品应有合格证和出厂质量证明文件，设备应有使用说明书并附有铭牌。4、采用和推广经鉴定并批准的新技术、新工艺、新材料、新设备等，应制定相应的施工技术标准。引进的设备，应按其技术文件要求施工。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]