[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149881":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149881,802,2,"多选题","关于地铁车站结构施工说法，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","混凝土结构施工前，施工单位应制定检测和试验计划，并应经监理单位批准后实施",true,{"key":16,"text":17,"correct":18},"B","墙体施工缝留置位置：水平施工缝在高出底板50～100mm处",false,{"key":20,"text":21,"correct":18},"C","顶、底板均可留置水平施工缝",{"key":23,"text":24,"correct":14},"D","模板及支架应根据安装、使用及拆除工况进行设计，并满足承载力、刚度、整体稳固性要求",{"key":26,"text":27,"correct":14},"E","钢筋进场时应抽取试件做力学性能和工艺性能试验","ADE","2020教材P368 \u002F 2019教材P369 （二）结构施工:（1）混凝土结构施工前，施工单位应制定检测和试验计划，并应经监理单位批准后实施。（2）模板及支架应根据安装、使用及拆除工况进行设计，并满足承载力、刚度、整体稳固性要求。（3）钢筋进场时应抽取试件做力学性能和工艺性能试验；钢筋安装时，受力钢筋的牌号、规格和数量必须符合设计要求，当需要进行钢筋代换时，应办理设计变更文件；预埋件、预留孔洞应位置准确并安装牢固。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]