[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149879":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149879,802,2,"多选题","下列关于悬臂浇筑检查项目正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","悬臂浇筑须对称进行，桥墩两侧平衡偏差经过验算确定，轴线挠度必须在设计规定范围内",false,{"key":16,"text":17,"correct":14},"B","梁体表面不得出现受力裂缝",{"key":19,"text":20,"correct":21},"C","悬臂合龙时，量侧梁体的高差必须在设计允许范围内",true,{"key":23,"text":24,"correct":21},"D","梁体线性平顺，相邻段接缝处无明显折弯和错台",{"key":26,"text":27,"correct":21},"E","梁体表面无孔洞、露筋、蜂窝麻面和宽度超过0.15mm收缩裂缝","CDE","2020教材P366 \u002F 2019教材P368 三、悬臂浇筑（一）主控项目（1）悬臂浇筑必须对称进行，桥墩两侧平衡偏差不得大于设计规定，轴线挠度必须在设计规定范围内。检査数量：全数检查。检验方法：检査监控量测记录。（2）梁体表面不得出现超过设计规定的受力裂缝。检查数量：全数检查。检验方法：观察或用读数放大镜观测。（3）悬臂合龙时，两侧梁体的高差必须在设计规定允许范围内。检查数量：全数检查。检验方法：用水准仪测量，检查测量记录。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]