[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149862":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149862,802,2,"多选题","《城镇道路工程施工与质量验收规范》CJJ1-2008中强制性条文规定：沥青混合料面层不得在（ ）时施工。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","下雨天",true,{"key":16,"text":17,"correct":18},"B","刮风天",false,{"key":20,"text":21,"correct":14},"C","下雪天",{"key":23,"text":24,"correct":18},"D","大雾天",{"key":26,"text":27,"correct":14},"E","最高气温低于5℃","ACE","2020教材P354 \u002F 2019教材P356 沥青面层不允许下雨时或下层潮湿时施工。城市快速路、主干路的沥青混合料面层在低于5度时严禁冬期施工。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]