[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149861":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149861,802,2,"多选题","道路雨期施工基本要求有（ ）等。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","以预防为主，掌握主动权",true,{"key":16,"text":17,"correct":18},"B","按常规安排工期",false,{"key":20,"text":21,"correct":14},"C","做好排水系统，防排结合",{"key":23,"text":24,"correct":14},"D","发现积水、挡水处及时疏通",{"key":26,"text":27,"correct":14},"E","准备好防雨物资","ACDE","2020教材P353 \u002F 2019教材P355 （一）雨期施工基本要求：（1）加强与气象台站联系，掌握天气预报，安排在不下雨时施工。（2）调整施工步序，集中力量分段施工。（3）做好防雨准备，在料场和搅拌站搭雨棚，或施工现场搭可移动的罩棚。（4）建立完善排水系统，防排结合；并加强巡视，发现积水、挡水处，及时疏通。（5）道路工程如有损坏，及时修复。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]