[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149854":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149854,802,2,"多选题","在施工项目质量控制过程中，对（ ）工程必须实施纠正方案及措施",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","质量有缺陷的",false,{"key":16,"text":17,"correct":18},"B","严重不合格的",true,{"key":20,"text":21,"correct":14},"C","质量偏差影响下一工序的",{"key":23,"text":24,"correct":18},"D","重大质量事故",{"key":26,"text":27,"correct":14},"E","影响结构安全的","BD","2020教材P348 \u002F 2019教材P350 （二）（4）对严重不合格或重大质量事故，必须实施纠正方案及措施。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]