[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149850":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149850,802,2,"多选题","施工质量因素控制的内容有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","人员控制",true,{"key":16,"text":17,"correct":14},"B","材料质量控制",{"key":19,"text":20,"correct":21},"C","质量通病控制",false,{"key":23,"text":24,"correct":14},"D","机械设备质量控制",{"key":26,"text":27,"correct":21},"E","不合格产品控制","ABD","2020教材P344 \u002F 2019教材P346 二）控制方法（1）应在施工过程中确定关键工序及特殊过程并明确其质量控制点及控制措施。影响施工质量的因素包括与施工质量有关的人员、施工机具、建筑材料、构配件和设备、施工方法和环境因素。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]