[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149844":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149844,802,2,"多选题","编制进度总结时应依据（ ）资料。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","进度计划",true,{"key":16,"text":17,"correct":18},"B","大事记",false,{"key":20,"text":21,"correct":14},"C","计划执行的实际记录",{"key":23,"text":24,"correct":14},"D","计划的检查结果",{"key":26,"text":27,"correct":14},"E","计划的调整资料","ACDE","2020教材P341 \u002F 2019教材P342 （一）（1）施工进度计划；（2）施工进度计划执行的实际记录；（3）施工进度计划检查结果；（4）施工进度计划的调整资料。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]