[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149843":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149843,802,2,"多选题","施工进度控制总结应包括的内容：合同工期目标及计划工期目标完成情况、施工进度控制经验与体会，以及（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","存在的问题及分析",true,{"key":16,"text":17,"correct":14},"B","科学方法的应用情况",{"key":19,"text":20,"correct":14},"C","改进意见",{"key":22,"text":23,"correct":24},"D","制定调整方案",false,{"key":26,"text":27,"correct":24},"E","外界干扰情况","ABC","2020教材P341 \u002F 2019教材P342 （1）合同工期目标及计划工期目标完成情况；（2）施工进度控制经验与体会；（3）施工进度控制中存在的问题及分析；（4）施工进度计划科学方法的应用情况；（5）施工进度控制的改进意见。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]