[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149842":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149842,802,2,"多选题","施工进度报告的内容包括进度计划执行情况综述、实际施工进度图、解决问题的措施以及（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程变更与价格调整",true,{"key":16,"text":17,"correct":18},"B","监理工程师的指令",false,{"key":20,"text":21,"correct":14},"C","索赔及工程款收支情况",{"key":23,"text":24,"correct":14},"D","进度偏差状况及原因",{"key":26,"text":27,"correct":14},"E","计划调整意见","ACDE","2020教材P340 \u002F 2019教材P342 （1）工程项目进度执行情况的综合描述。（注：包括监理工程师指令）（2）实际施工进度图。（3）工程变更，价格调整，索赔及工程款收支情况。（4）进度偏差的状况和导致偏差的原因分析。（5）解决问题的措施。（6）计划调整意见和建议。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]