[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149841":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149841,802,2,"多选题","进度计划检查审核的部分内容是（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","能否保证工程施工质量",true,{"key":16,"text":17,"correct":14},"B","施工的均衡性",{"key":19,"text":20,"correct":14},"C","能否保证工程施工安全",{"key":22,"text":23,"correct":14},"D","计划内容是否全面",{"key":25,"text":26,"correct":27},"E","进度计划调整",false,"ABCD","2020教材P340 \u002F 2019教材P341 一（二）（1）工程施工项目总进度目标和所分解的分目标的内在联系合理性，能否满足施工合同工期的要求。（2）工程施工项目计划内容是否全面，有无遗漏项目。（3）工程项目施工程序和作业顺序安排是否合理；是否需要调整；如何调整。（4）施工各类资源计划是否与进度计划实施的时间要求相一致；有无脱节；施工的均衡性如何。（5）总包方和分包方之间，各专业之间，在施工时间和位置的安排上是否合理，有无相互干扰，主要矛盾是什么。（6）工程项目施工进度计划的重点和难点是否突出；对风险因素的影响是否有防范对策和应急预案。（7）工程项目施工进度计划是否能保证工程施工质量和安全的需要。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]