[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149840":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149840,802,2,"多选题","在施工进度计划调整中，工作关系的调整主要是指施工（ ）的重新确认，目的在于利用施工的时间和空间进行合理的衔接。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","顺序的局部改变",true,{"key":16,"text":17,"correct":18},"B","操作工具",false,{"key":20,"text":21,"correct":14},"C","相互协作方式",{"key":23,"text":24,"correct":18},"D","材料供应",{"key":26,"text":27,"correct":18},"E","居住场地","AC","2020教材P340 \u002F 2019教材P341 三（3）在施工进度计划调整中，工作关系的调整主要是指施工顺序的局部改变或作业过程相互协作方式的重新确认，目的在于充分利用施工的时间和空间进行合理交叉衔接，从而达到控制进度计划的目的。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]