[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149838":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149838,802,2,"多选题","施工进度计划在实施过程中进行的必要调整，调整内容不包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","起止时间",false,{"key":16,"text":17,"correct":18},"B","检查方法",true,{"key":20,"text":21,"correct":14},"C","持续时间",{"key":23,"text":24,"correct":18},"D","考核办法",{"key":26,"text":27,"correct":14},"E","资源供应","BD","2020教材P339 \u002F 2019教材P341 （2）施工进度计划在实施过程中进行的必要调整必须依据施工进度计划检查审核结果进行。调整内容应包括：工程量、起止时间、持续时间、工作关系、资源供应。@##",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]