[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149837":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149837,802,2,"多选题","施工进度控度总目标应进行分解，不同的工程项目可分解为（ ）分目标。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","交工",true,{"key":16,"text":17,"correct":14},"B","时间",{"key":19,"text":20,"correct":21},"C","完工",false,{"key":23,"text":24,"correct":21},"D","单项",{"key":26,"text":27,"correct":14},"E","阶段","ABE","2020教材P339 \u002F 2019教材P340 （一）（2）按单位工程分解为交工分目标，制定子单位工程或分部工程交工目标。（3）按承包的专业或施工阶段分解为阶段分目标，重大市政公用工程可按专业工程分解进度目标分别进行控制；也可按施工阶段划分确定控制目标。（4）按年、季、月分解为时间分目标，适用于有形象进度要求时。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]