[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149835":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149835,802,2,"多选题","常用的表达工程进度计划方法有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","横道图",true,{"key":16,"text":17,"correct":14},"B","网络计划图",{"key":19,"text":20,"correct":21},"C","频率图",false,{"key":23,"text":24,"correct":21},"D","直方图",{"key":26,"text":27,"correct":21},"E","正态分布图","AB","2020教材P338 \u002F 2019教材P339 （三）常用的表达工程进度计划方法有横道图和网络计划图两种形式。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]