[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149824":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149824,802,2,"多选题","工程施工阶段按照施工总平面图要求，设置道路、组织排水以及（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","搭建临时设施",true,{"key":16,"text":17,"correct":14},"B","堆放物料",{"key":19,"text":20,"correct":14},"C","停放机具设备",{"key":22,"text":23,"correct":24},"D","设置交通警示牌",false,{"key":26,"text":27,"correct":24},"E","设置防火须知牌","ABC","2020教材P325 \u002F 2019教材P327 （3）工程施工阶段按照施工总平面图要求，设置道路、组织排水、搭建临时设施、堆放物料和停放机具设备等。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]