[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149823":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149823,802,2,"多选题","施工方案应包括的主要内容有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","施工方法的确定",true,{"key":16,"text":17,"correct":14},"B","技术措施的确定",{"key":19,"text":20,"correct":14},"C","施工机具的选择",{"key":22,"text":23,"correct":24},"D","工艺技术的选择",false,{"key":26,"text":27,"correct":14},"E","施工顺序的确定","ABCE","2020教材P312 \u002F 2019教材P314 4（1）施工方案是施工组织设计的核心部分，主要包括拟建工程的主要分项工程的施工方法、施工机具的选择、施工顺序的确定，还应包括季节性措施、四新技术措施以及结合工程特点和由施工组织设计安排的、黑钻压卷，金考典软件考前一周更新，下载链接 www.jinkaodian.com 根据工程需要采取的相应方法与技术措施等方面的内容。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]