[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149811":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149811,802,2,"多选题","以下选项中关于施工成本分析的任务说法正确的是（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","找出产生差异的原因",true,{"key":16,"text":17,"correct":14},"B","提出进一步降低成本的措施和方案",{"key":19,"text":20,"correct":21},"C","按统计方法加以系统整理，探索规律性",false,{"key":23,"text":24,"correct":14},"D","对成本计划的执行情况进行正确评价",{"key":26,"text":27,"correct":14},"E","正确计算成本计划的执行结果，计算产生的差异","ABDE","2020教材P309 \u002F 2019教材P311 二（一）施工成本分析的任务：（1）正确计算成本计划的执行结果，计算产生的差异；（2）找出产生差异的原因；（3）对成本计划的执行情况进行正确评价；（4）提出进一步降低成本的措施和方案。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]