[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149803":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149803,802,2,"多选题","同期记录的内容包括（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","人员设备闲置",true,{"key":16,"text":17,"correct":14},"B","对工期的延误",{"key":19,"text":20,"correct":14},"C","对工程损害程度",{"key":22,"text":23,"correct":14},"D","导致费用增加的项目",{"key":25,"text":26,"correct":27},"E","计算资料",false,"ABCD","2020教材P297 \u002F 2019教材P298 四、（2）同期记录的内容有：事件发生及过程中现场实际状况；导致现场人员、设备的闲置清单；对工期的延误；对工程损害程度；导致费用增加的项目及所用的工作人员、机械、材料数量、有效票据等。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]