[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149799":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149799,802,2,"多选题","由于工程投标时图纸不全，发生以承包方能力不可预见引起的索赔包括（ ）等。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","地质情况不清",true,{"key":16,"text":17,"correct":18},"B","征地拆迁",false,{"key":20,"text":21,"correct":18},"C","施工条件改变",{"key":23,"text":24,"correct":14},"D","工程量增加",{"key":26,"text":27,"correct":14},"E","施工工艺改变","ADE","2020教材P296 \u002F 2019教材P297 （四）由于工程投标时图纸不全，有些项目承包方无法作正确计算，如地质情况、软基处理等。该类项目一般发生的索赔有工程数量增加或需要重新投入新工艺、新设备等。计算方法：以承包方未预见的情况开始出现的第1天为起算日，终止日为索赔结束日。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]