[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149797":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149797,802,2,"多选题","施工过程中遇到的合同变更，如（ ）等，项目负责人必须掌握变更情况，遵照有关规定及时办理变更手续。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","标高",true,{"key":16,"text":17,"correct":14},"B","工程量增减",{"key":19,"text":20,"correct":14},"C","基线",{"key":22,"text":23,"correct":14},"D","质量及特性变更",{"key":25,"text":26,"correct":27},"E","工种",false,"ABCD","2020教材P293 \u002F 2019教材P294 三（一）（1）施工过程中遇到的合同变更，如工程量增减，质量及特性变更，工程标高、基线、尺寸等变更，施工顺序变化，永久工程附加工作、设备、材料和服务的变更等，项目负责人必须掌握变更情况，遵照有关规定及时办理变更手续。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]