[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149792":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149792,802,2,"多选题","下述（ ）因素出现后，发承包双方可根据合同约定，对合同价款进行变动的提出、计算和确认。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","法律法规变化",true,{"key":16,"text":17,"correct":14},"B","项目特征不符",{"key":19,"text":20,"correct":14},"C","工程量偏差",{"key":22,"text":23,"correct":24},"D","项目经理变更",false,{"key":26,"text":27,"correct":14},"E","不可抗力","ABCE","2020教材P291 \u002F 2019教材P292 三、合同价款调整因素出现后，发、承包双方根据合同约定，对合同价款进行变动的提出、计算和确认，一般规定：（1）法律法规变化；（2）工程变更；（3）项目特征不符；（4）工程量清单缺项；（5）工程量偏差；（6）计日工；（7）物价变化；（8）暂估价；（9）不可抗力；（10）提前竣工（赶工补偿）；（11）误期赔偿；（12）索赔；（13）现场签证；（14）暂列签证；（15）发、承包双方约定的其他调整事项。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]