[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149790":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149790,802,2,"多选题","因不可抗力事件导致的费用增加，由发包人承担的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","机械设备的损坏",false,{"key":16,"text":17,"correct":18},"B","工程本身的损害",true,{"key":20,"text":21,"correct":18},"C","发包人人员伤亡",{"key":23,"text":24,"correct":18},"D","现场保卫人员费用",{"key":26,"text":27,"correct":14},"E","施工人员伤亡","BCD","2020教材P291 \u002F 2019教材P292 （8）因不可抗力事件导致的费用，发、承包双方应按以下原则分担并调整工程价款：1）工程本身的损害、因工程损害导致第三方人员伤亡和财产损失以及运至施工现场用于施工的材料和待安装的设备的损害，由发包人承担；2）发包人、承包人人员伤亡由其所在单位负责，并承担相应费用；3）承包人的施工机械设备的损坏及停工损失，由承包人承担；4）停工期间，承包人应发包人要求留在施工现场的必要的管理人员及保卫人员的费用，由发包人承担；5）工程所需清理、修复费用，由发包人承担；6）工程价款调整报告应由受益方在合同约定时间内向合同的另一方提出，经对方确认后调整合同价款。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]