[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149788":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149788,802,2,"多选题","我国目前推行的部分费用综合单价不包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","人工费",false,{"key":16,"text":17,"correct":18},"B","税金",true,{"key":20,"text":21,"correct":14},"C","施工机械费",{"key":23,"text":24,"correct":18},"D","规费",{"key":26,"text":27,"correct":18},"E","措施费","BDE","2020教材P289 \u002F 2019教材P290 一（5）1）分部分项工程量清单应采用综合单价法计价。综合单价是完成一个规定计量单位的分部分项工程量清单项目或措施清单项目所需的人工费、材料费、施工机具使用费和企业管理费与利润，以及一定范围内的风险费用。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]