[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149785":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149785,802,2,"多选题","施工图预算是工程费用调整的依据，一般情况下不得调整，出现以下（ ）情况时可调整。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","地震灾害",true,{"key":16,"text":17,"correct":14},"B","洪水",{"key":19,"text":20,"correct":14},"C","政策性调整",{"key":22,"text":23,"correct":24},"D","材料涨价",false,{"key":26,"text":27,"correct":14},"E","重大设计变更","ABCE","2020教材P289 \u002F 2019教材P290 （3）施工图预算也是工程费用调整的依据。工程预算批准后，一般情况下不得调整。在出现重大设计变更、政策性调整及不可抗力等情况时可以调整。本试题中地震灾害和洪水属于不可抗力因素。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]