[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149779":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149779,802,2,"多选题","投标人应按招标人提供的工程量清单填报价格，填写的（ ）及工程量必须与招标人提供的一致。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","项目特征",true,{"key":16,"text":17,"correct":18},"B","市场价格",false,{"key":20,"text":21,"correct":14},"C","项目名称",{"key":23,"text":24,"correct":14},"D","计量单位",{"key":26,"text":27,"correct":14},"E","项目编码","ACDE","2020教材P284 \u002F 2019教材P285 （6）投标人应按招标人提供的工程量清单填报价格。填写的项目编码、项目名称、项目特征、计量单位、工程量必须与招标人提供的一致。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]