[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149772":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149772,802,2,"多选题","确定分包项目执行的规范标准和质量验收标准，应依据（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","工程技术",true,{"key":16,"text":17,"correct":14},"B","设计要求",{"key":19,"text":20,"correct":14},"C","有关规范",{"key":22,"text":23,"correct":24},"D","合同形式",false,{"key":26,"text":27,"correct":24},"E","分包模式","ABC","2020教材P281 \u002F 2019教材P282 （4）根据对工程技术、设计要求及有关规范的要求，确定分包项目执行的规范标准和质量验收标准，满足总承包方对分包项目提出的特殊要求。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]