[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149764":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149764,802,2,"多选题","基坑工程监控量测报警值应以监控量测项目的（）两个值控制。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","变化速率",true,{"key":16,"text":17,"correct":18},"B","日变化量",false,{"key":20,"text":21,"correct":14},"C","累计变化量",{"key":23,"text":24,"correct":18},"D","变化量",{"key":26,"text":27,"correct":18},"E","变化量、观测值","AC","2020教材P274 \u002F 2019教材P275 5. 监控量测预警基坑工程监控量测报警值应符合基坑工程设计的限值、地下主体结构设计要求以及监控量测对象的控制要求。基坑工程监控量测报警值应以监控量测项目的累计变化量和变化速率值控制。 基坑报警值应由基坑工程设计单位确定。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]