[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149760":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149760,802,2,"多选题","竣工总图编绘完成后，应经()审核、会签",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","建设单位技术负责人",false,{"key":16,"text":17,"correct":14},"B","设计单位技术负责人",{"key":19,"text":20,"correct":14},"C","施工单位技术负责人",{"key":22,"text":23,"correct":24},"D","监理单位总监理工程师",true,{"key":26,"text":27,"correct":24},"E","施工单位项目技术负责人","DE","2020教材P270 \u002F 2019教材P271 （三）竣工图编绘基本要求（3）竣工总图编绘完成后，应经施工单位项目技术负责人、监理单位总监理工程师审核、会签,@##",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]