[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149748":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149748,802,2,"多选题","下列关于GCL垫施工质量控制要点说法正确的是()。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","施工前均对基底进行修整和检验",true,{"key":16,"text":17,"correct":14},"B","GCL垫摊铺搭接宽度控制在250±50mm范围内，搭接处均匀撒膨润土粉，将两层垫间密封",{"key":19,"text":20,"correct":14},"C","GCL垫应无褶皱、无悬空现象，与基础层贴实",{"key":22,"text":23,"correct":24},"D","基底应顺设计坡向铺设GCL垫，采用十字或品形的上压下的搭接方式",false,{"key":26,"text":27,"correct":14},"E","GCL垫需当日铺设当日覆盖，避免雨雪天气施工，必要时采取覆盖防护措施","ABCE","2020教材P250 \u002F 2019教材P251 （三）质量控制要点：( 1 )填埋区基底检验合格，进行GCL垫铺设作业，每一工作面施工前均要对基底进行修整和检验。2 )对铺开的GCL垫进行调整，调整搭接宽度，控制在250士50mm范围内，拉平GCL垫，确保无褶皱、无悬空现象，与基础层贴实。3 )掀开搭接处上层的GCL垫，在搭接处均匀撒膨润土粉，将两层垫间密封，然后将掀开的GCL垫铺回。4 )根据填埋区基底设计坡向，GCL垫的搭接，尽量采用顺坡搭接，即采用上压下的搭接方式；注意避免出现十字搭接，应尽量釆用品形分布。5) GCL垫需当日铺设当日覆盖，遇有雨雪天气应停止施工，并将已铺设的GCL垫覆盖好。BCE。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]