[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149746":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149746,802,2,"多选题","下列工序中，属于GCL垫施工主要内容的是()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","吊运就位",false,{"key":16,"text":17,"correct":18},"B","GCL垫的摊铺",true,{"key":20,"text":21,"correct":18},"C","搭接宽度控制",{"key":23,"text":24,"correct":18},"D","搭接处两层GCL垫间撒膨润土",{"key":26,"text":27,"correct":14},"E","保护层摊铺","BCD","2020教材P250 \u002F 2019教材P251 （二）GCL垫施工主要包括GCL 垫的摊铺、搭接宽度控制、搭接处两层GCL垫间撒膨润土。答案选BCD",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]