[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149710":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149710,802,2,"多选题","燃气管道做通球扫线的前提应该是燃气管道及其附件（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","回填完毕",false,{"key":16,"text":17,"correct":14},"B","与干线连接",{"key":19,"text":20,"correct":21},"C","安装完毕",true,{"key":23,"text":24,"correct":14},"D","甲方验收合格",{"key":26,"text":27,"correct":21},"E","强度试验前试压前进行","CE","2020\u002F2019教材P241 一、管道吹扫管道及其附件组装完成并在试压前，应按设计要求进行气体吹扫或清管球清扫。 气体吹扫每次吹扫管道长度不宜超过500m,管道超过500m时宜分段吹扫。 吹扫球应按介质流动方向进行，以避免补偿器内套筒被破坏。吹扫结果可用贴有纸或白漆的木靶板置于吹扫口检查，5min内靶上无铁锈脏物则认为合格。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]