[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149704":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149704,802,2,"多选题","以下关于热力管道功能性试验说法正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","强度试验应在试验段内的管道接口防腐、保温施工及设备安装前进行",true,{"key":16,"text":17,"correct":18},"B","强度试验介质可用洁净水或压缩空气",false,{"key":20,"text":21,"correct":18},"C","当管道系统存在较大高度差时，试验压力以最高点压力为准，最低点的压力无要求",{"key":23,"text":24,"correct":18},"D","管线施工完成，现场组装的连接部位经检查合格即可进行强度试验",{"key":26,"text":27,"correct":14},"E","试运行中应对管道及设备进行全面检查，特别要重点检查支架的工作状况","AE","2020教材P229 \u002F 2019教材P230 管线施工完成后，经检查除现场组装的连接部位（如：焊接连接、法兰连接等）外，其余均符合设计文件和相关标准的规定后，方可以进行强度试验（D选项错误）；强度试验应在试验段内的管道接口防腐、保温施工及设备安装前进行，试验介质为洁净水（A选项正确、B选项错误）；当管道系统存在较大高差时，试验压力以最高点压力为准，同时最低点的压力不得超过管道及设备允许承受压力（C选项错误）；试运行中应对管道及设备进行全面检查，特别要重点检查支架的工作状况（E选项正确）。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]