[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149693":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149693,802,2,"多选题","热力管道施工前应该注意的问题有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","熟悉设计图纸，对图纸中不明白的地方，可以不用管",false,{"key":16,"text":17,"correct":18},"B","施工单位应在施工前取得设计文件、工程地质和水文地质等资料，组织工程技术人员熟悉施工图纸，进行图纸会审并参加设计交底会",true,{"key":20,"text":21,"correct":14},"C","热力管网中所用的阀门，可以没有制造厂的产品合格证和工程所在地测验部门的试验报告",{"key":23,"text":24,"correct":18},"D","降水施工时，应做好降水监测、环境影响监测和防治工作，保护地下水资源。",{"key":26,"text":27,"correct":18},"E","施工前，对施工影响范围的地上地下障碍物进行现场探查，制定相应的保护措施","BDE","2020教材P216 \u002F 2019教材P217 施工单位应在施工前取得设计文件、工程地质和水文地质等资料，组织工程技术人员熟悉施工图纸，进行图纸会审并参加设计交底会 降水施工时，应做好降水监测、环境影响监测和防治工作，保护地下水资源。 开工前需制定项目环境保护管理措施",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]