[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149689":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149689,802,2,"多选题","供热站试运行要求（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","试运行在单位工程验收合格，并且热源已具备供热条件后进行",true,{"key":16,"text":17,"correct":14},"B","试运行中应对管道及设备进行全面检查，特别要重点检查支架的工作状况",{"key":19,"text":20,"correct":14},"C","试运行的时间应为连续运行72h",{"key":22,"text":23,"correct":24},"D","试运行的时间应为连续运行36h",false,{"key":26,"text":27,"correct":14},"E","试运行应在建设单位、设计单位认可的条下进行","ABCE","2020\u002F2019教材P230 试运行在单位工程验收合格，并且热源已具备供热条件后进行。试运行前需要编制运行方案，并要在建设单位、设计单位认可的条下下连续运行72h。 试运行中应对管道及设备进行全面检查，特别要重点检查支架的工作状况",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]