[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149673":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149673,802,2,"多选题","给水排水工程中砌筑结构，砌筑沟道施工技术的基本要求：（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","砌筑前应检查地基或基础，确认其中线高程、基坑（槽）应符合规定，地基承载力符合设计要求，并按规定验收",true,{"key":16,"text":17,"correct":18},"B","接砌时，应将斜槎冲净并铺满砂浆，墙转角和交接处应与墙体分开砌筑",false,{"key":20,"text":21,"correct":14},"C","砌筑结构管渠宜按变形缝分段施工，砌筑施工需间断时，应预留阶梯形斜槎",{"key":23,"text":24,"correct":18},"D","砌体的沉降缝、变形缝应与基础的沉降缝、变形缝不能贯通",{"key":26,"text":27,"correct":14},"E","砌筑砂浆应饱满，砌缝应均勻不得有通缝或瞎缝，且表面平整","ACE","2020教材P208 \u002F 2019教材P209 一、基本要求：1.砌筑前应检查地基或基础，确认其中线高程、基坑（槽）应符合规定，地基承载力符合设计要求，并按规定验收。A对；3.砌筑砂浆应饱满，砌缝应均勻不得有通缝或瞎缝，且表面平整。E对；4.砌体的沉降缝、变形缝、止水缝应位置准确、砌体平整、砲体垂直贯通，缝板、止水带安装正确，沉降缝、变形缝应与基础的沉降缝、变形缝贯通。D错；5.砌筑结构管渠宜按变形缝分段施工，砌筑施工需间断时，应预留阶梯形斜槎；C对；接砌时，应将斜槎冲净并铺满砂浆，墙转角和交接处应与墙体同时砌筑。B错；",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]