[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149660":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149660,802,2,"多选题","压力管道试验准备工作包括（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","试验管段所有敞口应封闭，不得有渗漏水现象",true,{"key":16,"text":17,"correct":14},"B","试验管段不得用闸阀做堵板，不得含有消火栓、水锤消除器、安全阀等附件",{"key":19,"text":20,"correct":14},"C","水压试验前应清除管道内的杂物",{"key":22,"text":23,"correct":14},"D","应做好水源引接、排水等疏导方案",{"key":25,"text":26,"correct":27},"E","做好管道的强度检查",false,"ABCD","2020\u002F2019教材P206 2.准备工作：1）试验管段所有敞口应封闭，不得有渗漏水现象。2）试验管段不得用闸阀做堵板，不得含有消火栓、水锤消除器、安全阀等附件。3）水压试验前应清除管道内的杂物。4）应做好水源引接、排水等疏导方案。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]