[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149657":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149657,802,2,"多选题","下列（ ）水池（构筑物）工程施工应采取降排水措施。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","受地表水、地下动水压力作用影响的地下结构工程",true,{"key":16,"text":17,"correct":14},"B","采用排水法下沉和封底的沉井工程",{"key":19,"text":20,"correct":14},"C","基坑底部存在承压含水层，且经验算基底开挖面至承压含水层顶板之间的土体重力不足以平衡承压水水头压力，需要减压降水的工程",{"key":22,"text":23,"correct":24},"D","大型沉井",false,{"key":26,"text":27,"correct":24},"E","地下水池","ABC","2020教材P197 \u002F 2019教材P199 二、当构筑物无抗浮设计时，水池施工应采取抗浮措施（一）下列水池（构筑物）工程施工应采取降排水措施（1）受地表水、地下动水压力作用影响的地下结构工程；（2）采用排水法下沉和封底的沉井工程；（3）基坑底部存在承压含水层，且经验算基底开挖面至承压含水层顶板之间的土体重力不足以平衡承压水水头压力，需要减压降水的工程。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]