[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149656":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149656,802,2,"多选题","分节制作沉井时应（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","每节制作高度应符合施工方案要求，且第一节制作高度必须高于刃脚部分",true,{"key":16,"text":17,"correct":14},"B","混凝土施工缝处理应采用凹凸缝或设置钢板止水带，施工缝应凿毛并清理干净",{"key":19,"text":20,"correct":14},"C","沉井每次接高时各部位的轴线位置应一致、重合，及时做好沉降和位移监测",{"key":22,"text":23,"correct":24},"D","井内设有底梁或支撑梁时应与刃脚分别浇捣",false,{"key":26,"text":27,"correct":14},"E","必要时应对刃脚地基承载力进行验算，并采取相应措施确保地基及结构的稳定","ABCE","2020教材P195 \u002F 2019教材P197 （2）分节制作沉井1）每节制作高度应符合施工方案要求且第一节制作高度必须高于刃脚部分；井内设有底梁或支撑梁时应与刃脚部分整体浇捣。3）混凝土施工缝处理应采用凹凸缝或设置钢板止水带，施工缝应凿毛并清理干净；内外模板采用对拉螺栓固定时，其对拉螺栓的中间应设置防渗止水片；钢筋密集部位和预留孔底部应辅以人工振捣，保证结构密实。4）沉井每次接高时各部位的轴线位置应一致、重合，及时做好沉降和位移监测；必要时应对刃脚地基承载力进行验算，并采取相应措施确保地基及结构的稳定。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]