[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149654":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149654,802,2,"多选题","下列工作中属于沉井施工准备工作的是（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","按方案要求，进行施工平面布置，测设沉井中心桩，轴线控制桩，基坑开挖深度及边坡",true,{"key":16,"text":17,"correct":14},"B","沉井施工影响附近建（构）筑物、管线或河岸设施时，应采取控制措施，并应进行沉降和位移监测，测点应设在不受施工干扰和方便测量地方",{"key":19,"text":20,"correct":14},"C","地下水位应控制在沉井基坑以下0.5m，及时排除基坑内积水",{"key":22,"text":23,"correct":14},"D","基坑开挖应分层有序进行，保持平整和疏干状态",{"key":25,"text":26,"correct":27},"E","进行基础处理",false,"ABCD","2020教材P195 \u002F 2019教材P196 二、沉井准备工作：（一）基坑准备（1）按施工方案要求，进行施工平面布置，设定沉井中心桩，轴线控制桩，基坑开挖深度及边坡。（2）沉井施工影响附近建（构）筑物、管线或河岸设施时，应采取控制措施，并应进行沉降和位移监测，测点应设在不受施工干扰和方便测量地方。（3）地下水位应控制在沉井基坑以下0.5m，基坑内的水应及时排除；采用沉井筑岛法制作时，岛面标高应比施工期最高水位高出0.5m以上。（4）基坑开挖应分层有序进行，保持平整和疏干状态。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]