[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149650":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149650,802,2,"多选题","构筑物满水试验前的必备条件有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","池体的混凝土或砖、石砌体的砂浆已达到设计强度要求",true,{"key":16,"text":17,"correct":18},"B","选定好洁净、充足的水源",false,{"key":20,"text":21,"correct":14},"C","池体抗浮稳定性满足设计要求",{"key":23,"text":24,"correct":14},"D","池内外缺陷已修补完毕",{"key":26,"text":27,"correct":14},"E","各项保证试验安全的措施已满足要求","ACDE","2020教材P192 \u002F 2019教材P194 一、试验必备条件与准备工作：（一）满水试验前必备条件：1、池体的混凝土或砖、石砌体的砂浆已达到设计强度要求；池内清理洁净，池内外缺陷修补完毕。2、现浇钢筋混凝土池体的防水层、防腐层施工之前；装配式预应力混凝土池体施加预应力且锚固端封锚以后，保护层喷涂之前；砖砌池体防水层施工以后，石砌池体勾缝以后。3、设计预留孔洞、预埋管口及进出水口等已做临时封堵，且经验算能安全承受试验压力。4、池体抗浮稳定性满足设计要求。5、试验用的充水、充气和排水系统已准备就绪，经检查充水、充气及排水闸门不得渗漏。6、各项保证试验安全的措施已满足要求；满足设计的其他特殊要求。7、试验所需的各种仪器设备应为合格产品，并经具有合法资质的相关部门检验合格。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]