[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149647":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149647,802,2,"多选题","装配式预应力水池吊装的质量要点包括：（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","有裂缝的构件，应进行鉴定",true,{"key":16,"text":17,"correct":14},"B","预制柱、梁及壁板等构件应标注中心线，并在杯槽、杯口上标出中心线",{"key":19,"text":20,"correct":14},"C","预制构件应按设计位置起吊，曲梁宜采用三点吊装。吊绳与预制构件平面的交角不应小于45゜；当小于45゜时，应进行强度验算",{"key":22,"text":23,"correct":24},"D","预制构件安装就位后，应采取临时固定措施。曲梁应在梁的跨中临时支撑，待上部二期混凝土达到设计强度的50%及以上时，方可拆除支撑",false,{"key":26,"text":27,"correct":14},"E","安装的构件，必须在轴线位置及高程进行校正后焊接或浇筑接头混凝土","ABCE","2020教材P192 \u002F 2019教材P193 （1）安装前应经复验合格；有裂缝的构件，应进行鉴定。预制柱、梁及壁板等构件应标注中心线，并在杯槽、杯口上标出中心线；（2）预制构件应按设计位置起吊，曲梁宜采用三点吊装。吊绳与预制构件平面的交角不应小于45°；当小于45°时，应进行强度验算。预制构件安装就位后，应采取临时固定措施。曲梁应在梁的跨中临时支撑，待上部二期混凝土达到设计强度的75%及以上时，方可拆除支撑。安装的构件，必须在轴线位置及高程进行校正后焊接或浇筑接头混凝土。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]