[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149643":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149643,802,2,"多选题","下列关于无粘结预应力安装、张拉说法有误的是（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","锚固肋数量和布置应符合设计要求",false,{"key":16,"text":17,"correct":14},"B","上下相邻两无粘结预应力筋锚固位置应错开一个锚固肋",{"key":19,"text":20,"correct":21},"C","预应力筋的计算长度=张拉长度十锚固肋宽度十张拉工作长度",true,{"key":23,"text":24,"correct":21},"D","预应力筋安装中出现死弯时应及时进行角度、曲率调整",{"key":26,"text":27,"correct":21},"E","预应力筋可采用特殊接头进行接长使用","CDE","2020教材P190 \u002F 2019教材P191 3、（1）锚固肋数量和布置，应符合设计要求；A对；（2）安装时，上下相邻两无粘结预应力筋锚固位置应错开一个锚固肋；B对；每段无粘结预应力筋的计算长度应考虑加入一个锚固肋宽度及两端张拉工作长度和锚具长度；C错（4）无粘结预应力筋不应有死弯，有死弯时必须切断；D错；（5）无粘结预应力筋中严禁有接头。E错；",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]