[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149636":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149636,802,2,"多选题","给水与污水处理构筑物和设备安装、试验、验收完成后，正式运行前必须进行全厂试运行，试运行的内容（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","检验设备的稳定性",false,{"key":16,"text":17,"correct":14},"B","检验设备的联动性",{"key":19,"text":20,"correct":21},"C","检验、试验和监视运行，设备首次启动，以试验为主，通过试验掌握运行性能",true,{"key":23,"text":24,"correct":21},"D","按规定全面详细记录试验情况，整理成技术资料",{"key":26,"text":27,"correct":21},"E","正确评估试运行资料、质量检查和鉴定资料等，并建立档案","CDE","2020教材P186 \u002F 2019教材P188 主要内容（1）检验、试验和监视运行，设备首次启动，以试验为主，通过试验掌握运行性能。（2）按规定全面详细记录试验情况，整理成技术资料。（3）正确评估试运行资料、质量检查和鉴定资料等，并建立档案。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]