[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149620":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149620,802,2,"多选题","在流沙地层中，预制沉井法施工应采取不排水下沉湿式沉井方法施工，不排水下沉可分为（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","水力机械下沉",false,{"key":16,"text":17,"correct":18},"B","水下抓土下沉",true,{"key":20,"text":21,"correct":18},"C","空气吸泥下沉",{"key":23,"text":24,"correct":18},"D","水下水力吸泥下沉",{"key":26,"text":27,"correct":14},"E","机械挖土下沉","BCD","2020教材P182 \u002F 2019教材P184 不排水下沉分为水下抓土下沉、水下水力吸泥下沉、空气吸泥下沉。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]