[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149602":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149602,802,2,"多选题","在各种开挖方法中，初期支护拆除量小的方法是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","CRD法",false,{"key":16,"text":17,"correct":18},"B","CD法",true,{"key":20,"text":21,"correct":18},"C","单侧壁导坑法",{"key":23,"text":24,"correct":14},"D","中洞法",{"key":26,"text":27,"correct":14},"E","侧洞法","BC","2020教材P165 \u002F 2019教材P167 表1K413041：CRD工法初期支护拆除量大；CD工法初期支护拆除量小；单侧壁导坑法初期支护拆除量小；侧洞法和中洞法初期支护拆除量大。@##",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]