[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149592":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149592,802,2,"多选题","盾构施工步骤一般粗略分为（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","始发",true,{"key":16,"text":17,"correct":14},"B","正常掘进",{"key":19,"text":20,"correct":14},"C","到达",{"key":22,"text":23,"correct":24},"D","穿越环境风险源",false,{"key":26,"text":27,"correct":24},"E","穿越不良地质","ABC","2020教材P147 \u002F 2019教材P148 盾构施工一般分为始发、正常掘进和接收三个阶段。始发是指盾构自始发工作井内盾构基座上开始掘进，到完成初始掘进（通常50~100m）止。始发结束后要拆除临时管片、临时支撑和反力架，分体始发时还要将后续台车移入隧道内，以便后续正常掘进。接收是指自掘进距接收工作井100m到盾构到达接收工作井内接收基座上止。从施工安全的角度讲，始发与接收是盾构法施工两个重要阶段。为保证盾构始发与接收施工安全，洞口土体加固施工必须满足设计要求。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]